Laing O’Rourke Noarlunga Line Rail Electrification Site Office

Laing O’Rourke is a multinational construction company headquartered in Dartford, United Kingdom. Laing O’Rourke was awarded the rail electrification project for the Noarlunga Line.

Problem / Customer Requirement

In 2012 Laing O’Rourke requested quotes to seat 85 people in a new site office for the Noarlunga Line Rail Electrification project.

There were 73 work stations in open plan areas and 12 work stations in offices.

The project requirements were as follows:

  • Work with Laing O’Rourke to design and finalise the layout for the site office
  • The furniture had to be designed to allow relocation to a future site office in two years
  • Custom colours to match the company branding
  • Manufacture and install the fit out within three to four weeks
  • 85 workstations, 94 screens

Action Taken / Solution Steps

  • Creative Systems worked with Laing O’Rourke to develop a layout that saved over 9% of the office partition cost by improving the efficiency of the originally proposed layout
  • Creative Systems manufactured and installed the office partitions within the requested time frame
  • Order received 9/8/12
  • Order completed 31/8/12
  • Creative Systems worked with all other trades to ensure a safe and productive environment

Result / Outcome for Customer

The customer received the handover of the fit out within the requested time frame.

Product notes

Aluminium colour: Precious Silver Pearl

Fabric: RIM Harmony Ebony BA9 & Ming BA17

Power: Soft wired

Laing O'Rourke fitout
Laing O'Rourke fitout
Laing O'Rourke fitout
Laing O'Rourke fitout